“Eurasia” Boarding house
In 2021, a wastewater treatment facility with a capacity of 500 m³/day was built for the "Eurasia" boarding house. This is an important achievement in the field of infrastructure, providing high quality wastewater treatment and improving the environmental situation in the region. Modern technologies and equipment used during construction allow for effective removal of pollutants, which contributes to environmental protection and improving the comfort of living in the guesthouse. Thanks to this project, the boarding house “Eurasia” became an example of responsible attitude to ecology and sustainable development.
Мощность
500 m3/day
Кол-во жителей
2500 person
Локация
Issyk-Kul region, Kara-Oi v.
Потребление электроэнергии
12 kW/hour
Конструкция
Reinforced concrete
Год реализации
2021
Удельный расход электроэнергии
0,05 kW/hour
Оставить заявку
Сделать природу чище