rb logo

“Eurasia” Boarding house

In 2021, a wastewater treatment facility with a capacity of 500 m³/day was built for the "Eurasia" boarding house. This is an important achievement in the field of infrastructure, providing high quality wastewater treatment and improving the environmental situation in the region. Modern technologies and equipment used during construction allow for effective removal of pollutants, which contributes to environmental protection and improving the comfort of living in the guesthouse. Thanks to this project, the boarding house “Eurasia” became an example of responsible attitude to ecology and sustainable development.

Power

500 m3/day

Number of inhabitants

2500 person

kg flag

Location

Issyk-Kul region, Kara-Oi v.

Electricity consumption

12 kW/hour

Design

Reinforced concrete

Realization date

2021

Удельный расход электроэнергии

0,05 kW/hour

“Eurasia” Boarding house - 0 “Eurasia” Boarding house - 1 “Eurasia” Boarding house - 2 “Eurasia” Boarding house - 3 “Eurasia” Boarding house - 4 “Eurasia” Boarding house - 5
“Eurasia” Boarding house - 0 “Eurasia” Boarding house - 1 “Eurasia” Boarding house - 2 “Eurasia” Boarding house - 3 “Eurasia” Boarding house - 4 “Eurasia” Boarding house - 5

Leave a request

Make nature cleaner