rb logo

Volodarskogo settlement

This project was carried out jointly with Czech colleagues from TopolWater s.r.o. It was an incredibly interesting and at the same time difficult project. Firstly, its scale and size, and secondly, the level of equipment and innovations in solving engineering problems. The general customer was the administration of the Moscow region. Our customer was the local construction company JSC Stroyteploservice, which also carried out the general construction part of this project. The sewage treatment plant was built to receive wastewater from the village of Volodarsky, Leninsky district, Moscow region, taking into account the increase in the population of this village. The technology is equipped with coarse pretreatment with a sand catcher, chemical phosphorus removal and tertiary aftertreatment with drum filters and a UV bactericidal device. The requirements for the quality of purified water were high, since the water according to the project should be discharged into the nearest river.

Power

5 000 m3/day

Number of inhabitants

20 000 person

kg flag

Location

Volodarsky settlement, Leninsky district, Moscow region

Electricity consumption

400 кW/hour

Size

70m х 25m х 6m

Design

Reinforced concrete tanks, brick building

Realization date

2017

Удельный расход электроэнергии

0,02 кW/m3

Volodarskogo settlement - 0 Volodarskogo settlement - 1 Volodarskogo settlement - 2 Volodarskogo settlement - 3 Volodarskogo settlement - 4 Volodarskogo settlement - 5 Volodarskogo settlement - 6 Volodarskogo settlement - 7 Volodarskogo settlement - 8 Volodarskogo settlement - 9
Volodarskogo settlement - 0 Volodarskogo settlement - 1 Volodarskogo settlement - 2 Volodarskogo settlement - 3 Volodarskogo settlement - 4 Volodarskogo settlement - 5 Volodarskogo settlement - 6 Volodarskogo settlement - 7 Volodarskogo settlement - 8 Volodarskogo settlement - 9

Leave a request

Make nature cleaner